#1 ·
Hey everyone,
So, I just closed on a condo and I’ve got a bit of a situation on my mind...
I haven't actually moved in yet, but I was looking over my preliminary purchase agreement and this part caught my eye:
Article 8:
The projected completion date for the building and the handover of the unit is December 31, 2010.
Article 9:
Both parties agree that the seller won't be held liable for missing the deadline in Article 8 if any of these things happen:
- Acts of God/Force Majeure
- Delays in expanding the primary or secondary utility grids, provided it's not the seller's fault.
- Any actions or mandates from government agencies or local authorities that mess with the planned construction schedule.
If one of those situations pops up, the seller promises to let the buyer know what the new completion date will be.
However, the seller also agrees that if they are at fault for a delay in delivering the unit, they'll pay the buyer an amount equal to the average local monthly rent—which we're setting right here in this contract at $220 per month—for every 30 days the delivery is late.
So, here's the deal... the whole building still isn't finished (they're still working on the 5th floor), even though my specific unit on the 2nd floor was actually completed about three weeks ago.
My question is, do I actually have the right to go after them for those penalties ($220 for every month they're late handing it over)? Or is there some kind of loophole where they might not have to pay me despite what the contract says?
THANKS!
So, I just closed on a condo and I’ve got a bit of a situation on my mind...
I haven't actually moved in yet, but I was looking over my preliminary purchase agreement and this part caught my eye:
Article 8:
The projected completion date for the building and the handover of the unit is December 31, 2010.
Article 9:
Both parties agree that the seller won't be held liable for missing the deadline in Article 8 if any of these things happen:
- Acts of God/Force Majeure
- Delays in expanding the primary or secondary utility grids, provided it's not the seller's fault.
- Any actions or mandates from government agencies or local authorities that mess with the planned construction schedule.
If one of those situations pops up, the seller promises to let the buyer know what the new completion date will be.
However, the seller also agrees that if they are at fault for a delay in delivering the unit, they'll pay the buyer an amount equal to the average local monthly rent—which we're setting right here in this contract at $220 per month—for every 30 days the delivery is late.
So, here's the deal... the whole building still isn't finished (they're still working on the 5th floor), even though my specific unit on the 2nd floor was actually completed about three weeks ago.
My question is, do I actually have the right to go after them for those penalties ($220 for every month they're late handing it over)? Or is there some kind of loophole where they might not have to pay me despite what the contract says?
THANKS!